What Is Day 1?
When the launch scope keeps growing because nobody drew the line.
The problem I have seen most often between business and IT is that nobody has clearly defined what must be ready on Day 1, the day of launch.
Without that definition the scope keeps growing. Every new request is added to the launch, because there is no agreed basis for saying it can come later. The timeline stays the same while the work behind it increases.
The question that needs an answer early is a simple one:
What exactly do we need on Day 1?
Here’s what I learned
The answer has to come from the business strategy, so I start there with three questions:
- 01What does the business need to achieve at launch?
- 02Which key milestones does the strategy depend on?
- 03What can come afterwards, in complementary releases?
Day 1 then becomes the scope the business needs to reach its launch goal. Everything else is planned into the releases that follow, each with its own date.
A request that arrives later goes through the same decision. Either it is needed for Day 1, or it is assigned to one of the releases after it.
The business still gets what it asked for, in an agreed order, and the launch date stays realistic because the Day 1 scope has stopped growing. The PMO’s part is to make sure that decision is taken and written down, and to bring every new request back to it.
What the program should be able to say at any point is:
“This is what we launch with on Day 1, and this is what follows in each release after it.”
Does your program have an agreed definition of Day 1?